Funding technical debt as a portfolio item, not a backlog chore
In brief
Why technical debt rarely wins funding, how to price its interest and principal in dollars, and three ways to fund remediation, with a worked example.
Steve Elliott · · 7 min read
On this page
- What did Cunningham and Fowler actually say about technical debt?
- Why does technical debt rarely get funded?
- How do you price technical debt in money?
- Worked example: should the portfolio fund a $420,000 remediation?
- Which funding mechanism should you use?
- How should the portfolio track debt after funding?
- Sources
Technical debt gets funded when it arrives at the investment committee in the same format as everything else: a cost, a dated benefit and a payback period. Price the interest you pay each year on a specific system, price the principal it would take to remove it, and fund the items where the first is large against the second.
In our view, debt stays on the team backlog because it has no business case, not because leaders don't care. Below, we read the two original sources on the metaphor, set out what "interest" means in money, work one illustrative example and compare three ways to fund the result. For the basics, see our general guide to technical debt.
What did Cunningham and Fowler actually say about technical debt?
Ward Cunningham introduced the metaphor in an OOPSLA '92 experience report on WyCash, a portfolio management system for cash securities built in Smalltalk. "Shipping first time code is like going into debt," he wrote. A little debt speeds development if it is repaid promptly with a rewrite; the danger comes when it is not. He counted every minute spent on not-quite-right code as interest, and warned that whole engineering organizations can be brought to a standstill by an unconsolidated implementation. A 2009 addendum on the same page links a short video in which Cunningham discusses the metaphor's role as a defense of refactoring, a word the 1992 text does not use.
Martin Fowler's technical debt article, rewritten in 2019, makes the terms precise. Interest is the extra effort each new feature costs because of the cruft; principal is the work to clean it up. His example: a feature takes six days instead of four, and cleanup takes five. Cleanup loses money for one feature and pays back across three. Two further points matter for funding. Interest is only paid when you change the code, so crufty but stable areas can be left alone. And because productivity can't be measured, he says, none of these costs are objectively measurable.
His 2009 technical debt quadrant crosses deliberate with inadvertent and prudent with reckless. "A mess is a reckless debt," he writes, and he still counts it as debt. He also argues that prudent, inadvertent debt is inevitable even for excellent teams, who may need as much as a year of building before they understand the right design.
Why does technical debt rarely get funded?
In our view, four features of debt work against it in a funding round:
- The benefit is avoided cost. Remediation removes spend that never appears as a line item: extra hours inside teams' run budgets, incident time, delay. We think committees find new revenue easier to fund than cost avoidance.
- The principal is visible and the interest is not. A remediation request names a team and a quarter. The interest is spread across every change to the system, so nobody owns the total.
- Precision is missing. Fowler's warning that these costs aren't objectively measurable is honest, and an engineering estimate without a range looks weak next to a sales forecast.
- Requests arrive as backlog items. A ticket to "refactor the pricing module" carries no dollar figure and no link to a business capability.
None of this means the debt is unimportant. Peer-reviewed research that measures it suggests the interest can be large. In a longitudinal study of 43 developers at six companies, with surveys twice a week for seven weeks, Besker, Martini and Bosch found "developers waste, on average, 23% of their time due to TD." A replication at a separate company in Germany found 28.5% of the time spent on the reported tasks, a figure the authors say doesn't generalize to all working time. Both figures are self-reported, the sample is small and the authors caution against reading causation into their correlations. In about a quarter of occasions, developers also said existing debt forced them to add new debt, though usually only to a small extent. We treat this as evidence that interest is worth measuring locally, not as a number to put in your own business case.
How do you price technical debt in money?
Price it per system, not per estate. We use three interest components and one principal:
| Component | What to measure | Where the data usually lives |
|---|---|---|
| Extra effort per change | Share of team time spent working around the debt, times the fully burdened labor rate | Team estimates per change, sampled over a few sprints |
| Incident cost | Incidents traced to the debt, times response labor plus business loss per incident | Incident and problem records |
| Delay cost | Weeks of delay on value-bearing changes, times the value per week of each change | Roadmap and business case dates |
| Principal | Remediation labor plus tooling, environments and testing | Engineering estimate, given as a range |
A note on lead time. DORA defines change lead time as the time from commit to deployment in production. Much of the delay that debt causes happens before the commit, in analysis, design and working around the code, so DORA's measure will catch only part of it. We'd use it as a trend signal and estimate delay against roadmap dates.
Worked example: should the portfolio fund a $420,000 remediation?
All numbers below are illustrative. They come from no company and are chosen to show the mechanics.
The system. An order-pricing service owned by a team of 8 engineers at an assumed fully burdened $180,000 a year each, or $1.44 million a year. The capability roadmap plans heavy change to pricing over the next three years.
The interest today.
- Extra effort: the team estimates 20% of its time goes to working around the debt. 0.20 × $1.44M = $288,000 a year.
- Incidents: 10 incidents a year traced to the debt, at $25,000 each in lost orders and on-call and support time outside the team (the team's own time is already in the 20%). That is $250,000 a year.
- Delay: two pricing changes a year slip 6 weeks each, and each is worth $10,000 a week once live. 2 × 6 × $10,000 = $120,000 a year.
Total interest: $288,000 + $250,000 + $120,000 = $658,000 a year.
The principal. 4 engineers for 6 months is 2 engineer-years, or $360,000, plus $60,000 for test automation and environments: $420,000.
The expected benefit. Remediation won't remove all the interest. The team estimates extra effort falls from 20% to 5% (saving $216,000), incidents fall from 10 to 3 (saving $175,000) and delay halves (saving $60,000). That is $451,000 a year, about 69% of today's interest.
| Illustrative item | Year 1 | Year 2 | Year 3 | Total |
|---|---|---|---|---|
| Principal | −$420,000 | $0 | $0 | −$420,000 |
| Interest saved (from month 7 in year 1) | $225,500 | $451,000 | $451,000 | $1,127,500 |
| Net | −$194,500 | $451,000 | $451,000 | $707,500 |
Payback comes about 11 months after the work finishes, or about 17 months from the start ($420,000 ÷ $451,000 × 12 ≈ 11.2 months). Discounting each year's net at an assumed 10%, at year end, gives about $535,000 over three years, so the answer holds.
Now test the input that matters most. Fowler's point that interest is paid only on change cuts both ways. Suppose the roadmap moved pricing work elsewhere: change volume fell by two-thirds, incidents (mostly triggered by changes) fell with it, and fewer changes meant fewer slipped weeks. Savings drop to about a third, roughly $150,000 a year. Payback then comes about 34 months after the work ends, and the three-year net turns negative: $75,000 + $150,000 + $150,000 − $420,000 = −$45,000. Compare a stable reporting module with $15,000 a year of interest and a $200,000 cleanup: even if cleanup removed all of it, payback would take more than 13 years, and we'd leave it alone.
Which funding mechanism should you use?
We see three, and in our view most organizations need more than one.
| Mechanism | How it works | Fits | Weakness |
|---|---|---|---|
| Fixed capacity share | A set share of team or train capacity is reserved for debt and enabler work, and reviewed periodically | Small, local debt paid off gradually, which Fowler recommends | Invisible to the portfolio; no link between spend and interest removed |
| Explicit portfolio item | Remediation competes for funding with a business case like the one above | Large debt with a clear owner and measurable interest | Needs estimation effort; can lose to revenue items on timing |
| Tied to capability investment | Remediation is a funded part of the investment that will change the system | Debt in systems the roadmap is about to change heavily | Only works where a capability investment exists to carry it |
SAFe 6.0, which Scaled Agile's June 2026 AI-Native SAFe release does not replace, describes the fixed-share mechanism: Product and Solution Management can decide how much of an agile release train's effort to reserve for each activity type for the next planning interval (PI), and review that allocation periodically. That page recommends no percentage, and we don't think one exists that suits every estate.
In our view, the third mechanism is the most underused. The example's payback depends on future change volume, and the roadmap already knows that volume. If a capability-based planning cycle funds a new pricing capability, the remediation belongs inside that case, because otherwise the new investment pays the interest on every change it makes. Our post on tracing strategy to capabilities to cost covers how to make that link visible.
How should the portfolio track debt after funding?
Treat each funded item like any investment: a baseline, a target and a review date. Record the three interest components before work starts, and measure them again two and four quarters after it ends. If extra effort and incidents didn't fall, say so and use the miss to calibrate the next estimate. Whether any remediation labor can be capitalized is an accounting question; our post on software capitalization describes the rules, and your controller decides.
In our view, debt competes fairly for money once its interest, the roadmap that drives it and the IT portfolio decision sit in one operating model, so the committee sees the cost of not paying alongside the cost of paying.
Sources
- Ward Cunningham, The WyCash Portfolio Management System, OOPSLA '92 Experience Report, March 26, 1992, with 2009 addendum, accessed November 23, 2026
- Martin Fowler, Technical Debt, May 21, 2019 (first posted October 1, 2003)
- Martin Fowler, Technical Debt Quadrant, October 14, 2009
- Terese Besker, Antonio Martini and Jan Bosch, Software developer productivity loss due to technical debt: a replication and extension study examining developers' development work, Journal of Systems and Software 156: 41–61, 2019, doi:10.1016/j.jss.2019.06.004
- DORA, DORA's software delivery performance metrics, last updated January 5, 2026
- Scaled Agile, ART and solution train backlogs, SAFe 6.0, last updated October 9, 2023
- Scaled Agile, Framework home page, SAFe 6.0, modified September 25, 2026
- Scaled Agile, New Release: AI-Native SAFe is the Operating Model for the AI-Native Organization, June 23, 2026
Frequently asked questions
What is the difference between technical debt principal and interest?
In Martin Fowler's terms, principal is the work needed to remove the cruft, and interest is the extra effort every new change costs while the cruft remains. Ward Cunningham's 1992 report counted time spent on not-quite-right code as interest. For funding, we also count incident cost and delay on value-bearing changes as interest, and price each in dollars per year.
What percentage of capacity should go to technical debt?
No primary source we found recommends one. SAFe 6.0 describes trains reserving a share of capacity for each activity type per planning interval, reviewing it periodically, but gives no recommended figure. In our view, a fixed team share suits small, local debt. Large debt in heavily changed systems should be funded as an explicit portfolio item or inside the capability investment that will change the system.
How much developer time does technical debt waste?
One peer-reviewed study, Besker, Martini and Bosch (2019), found developers self-reported wasting 23% of their working time on average because of technical debt. It surveyed 43 developers at six companies twice a week for seven weeks, and a replication at another company found 28.5% of time on reported tasks. The sample is small and self-reported, so we'd measure your own systems rather than reuse the figure.
When should technical debt not be paid down?
When the code rarely changes. Fowler notes that interest is paid only when you work in the affected code, so stable areas can be left alone. In our illustrative example, a reporting module with $15,000 a year of interest and a $200,000 cleanup would take more than 13 years to pay back, so we would leave it.
Steve Elliott
Published November 23, 2026
More on Enterprise Architecture
Capability maps, TOGAF, rationalization.
Keep reading
Demystifying Technical Debt: A Comprehensive Guide
Technical debt is the future cost of shortcuts in software. Learn what causes it, how it slows teams down and how to manage it before it gets out of hand.
Building a business capability map that portfolio decisions actually use
How to build a capability map that informs funding: what a capability is and isn't, levels and naming, and a worked example with instances and heat ratings.
Eliminate Data Entry, Not Strategic Context
New in Dotwork: agents that collect status in Slack so teams stop re-entering updates, an orchestrator agent for leaders, and Agent Studio for building governed enterprise agents.
Project vs product funding: what changes in your IT cost model
Moving from project to product funding changes the cost object, allocation, capex evidence, budget cadence and how success is measured. What to change.