Quick wins in a transformation: when they build momentum and when they distort the portfolio

In brief

What Kotter, Weick and Amabile actually say about short-term wins, a five-question test for a good quick win, and a worked portfolio showing the crowd-out.

Steve Elliott

Steve Elliott · · 7 min read


On this page
  1. What did Kotter actually say about short-term wins?
  2. What does the research on small wins add?
  3. How do quick wins distort a transformation portfolio?
  4. Worked example: how quick wins can crowd out a foundational initiative
  5. What makes a good quick win?
  6. How should a transformation office govern quick wins?
  7. Sources

Quick wins build momentum when they are planned outcomes on the path to the transformation's main benefit, finished and in use, and paid for without delaying the foundational work. They distort the portfolio when they are chosen because they are easy, when they book benefits the main program would have delivered anyway, or when they take the scarce people the foundation needs.

The sources usually cited for quick wins are more demanding than the phrase suggests. John Kotter's 1995 article asks for deliberately planned wins inside one to two years, not a 90-day sprint. Karl Weick's small wins are complete and implemented, not announced. In our view, a transformation office should apply that standard and count what quick wins cost in delay, not only what they deliver early.

What did Kotter actually say about short-term wins?

In "Leading Change: Why Transformation Efforts Fail" (Harvard Business Review, March–April 1995), Kotter drew on watching more than 100 companies try to change. Short-term wins are step 6 of his eight, "Planning for and Creating Short-Term Wins", and error 6 is failing to do so. Step 7 is consolidating improvements. Kotter Inc.'s current page, which presents the 2014 accelerators, still lists "Generate Short-Term Wins" sixth. The details matter more:

  • Wins are planned, not found. "Creating short-term wins is different from hoping for short-term wins." Kotter wants visible performance improvements planned, set as goals in the yearly planning system, and the people involved rewarded.
  • "Short-term" means 12 to 24 months. His argument is that most people won't stay with a long effort unless they see convincing evidence within that window.
  • His worked example was not trivial. A manufacturer's guiding coalition picked a new product about six months into the renewal effort and launched it about 20 months in. It was chosen because it could be launched relatively quickly, a small dedicated team could handle it, it had upside, and the team could work outside the existing departmental structure.
  • Pressure can help. Kotter accepts that managers complain about being forced to produce wins and argues the pressure keeps urgency up and forces analysis that can clarify or revise the vision.

His error 7, declaring victory too soon, is the other half. In a dozen reengineering efforts he watched, all but two declared victory after the first major project was done, two to three years in; within two more years the useful changes slowly disappeared. Successful leaders, he wrote, use the credibility of short-term wins to tackle bigger problems. Our comparison of change models covers the rest of the eight steps.

What does the research on small wins add?

Other sources cited alongside Kotter carry conditions too.

Karl Weick's "Small Wins: Redefining the Scale of Social Problems" (American Psychologist, January 1984) defines a small win as "a concrete, complete, implemented outcome of moderate importance." His argument is psychological: framing a problem as vast raises arousal to the point where the quality of thought and action declines, so smaller framings can produce better work. He also says small wins are scattered and cohere only by moving in the same general direction, and that a tidy story told afterward should not be mistaken for orderly implementation. In our view, that warns anyone presenting a list of quick wins as a strategy.

Teresa Amabile and Steven Kramer's "The Power of Small Wins" (Harvard Business Review, May 2011) and their book The Progress Principle rest on nearly 12,000 daily diary entries from 238 employees in seven companies. They found that progress in meaningful work did more than anything else to support a positive inner work life. Harvard Business School's Working Knowledge reported their finding that setbacks had an effect two to three times stronger than progress. Their subject is the motivation of white-collar employees on projects, not portfolio choices, and their condition is meaningful work.

Michael Watkins' The First 90 Days has a chapter titled "Secure Early Wins". In a 2003 Working Knowledge interview he said credibility and early wins lay a foundation for longer-term success. His subject is a leader in a new role, a different unit of analysis from a multi-year program.

SourceWhat counts as a winTimescaleCondition
Kotter, HBR 1995Visible performance improvement, planned and rewarded12 to 24 monthsUsed to tackle bigger problems, not to declare victory
Weick, 1984Concrete, complete, implemented outcome of moderate importanceNot fixedWins are scattered; coherence comes from direction
Amabile and Kramer, 2011Progress, even small, in meaningful workDailySetbacks weigh more than progress
Watkins, 2003Early wins that build credibilityA leader's first monthsApplies to a person in a new role

None of them recommends choosing work only because it is quick: Kotter's example also needed upside and a team devoted to the vision. In our view, that is where quick-win programs drift.

How do quick wins distort a transformation portfolio?

In our view, three mechanisms do the damage.

  • Easy instead of meaningful. A win picked because it is cheap and fast can sit off the path to the main benefit. It shows motion, not progress, and Amabile and Kramer's condition of meaningful work isn't met.
  • Borrowing from the future. A license cut on a system the main program will decommission, a one-off rebate booked as recurring, or a deferred refresh counted as savings all move benefit forward or overstate it. It surfaces later in the benefits register; the distinction between run-rate savings and in-year effects is covered in our post on run-rate vs in-year savings.
  • Starving the foundation. Quick wins and foundational work can need the same few people: data engineers, integration specialists, process owners. Every month they spend on a win is a month the foundation slips, and in the example below the foundation carries most of the value.

Worked example: how quick wins can crowd out a foundational initiative

All numbers here are illustrative. Take a finance transformation with one shared team of 6 data and integration specialists, so 6 person-months of capacity a month.

  • Foundation. Consolidate the general ledgers and data model. It needs 72 person-months, so 12 months with the whole team, and delivers $6.0 million a year once live.
  • Quick wins. Four smaller fixes, each needing 9 person-months (36 in all, or 6 months of the team), together worth $2.0 million a year.

Benefits start the month after go-live at full run rate; present values discount monthly benefits at 10% a year. Three sequences, each over 36 months:

  • A, quick wins first. Wins land at month 6; the foundation runs months 7 to 18.
  • B, foundation first. The foundation lands at month 12; wins run months 13 to 18.
  • C, foundation sliced. A first release for one business unit goes live at month 6 with $1.0 million a year of the foundation's benefit; slicing costs a month, so the full foundation lands at month 13; wins run months 14 to 19.
Illustrative benefit ($M)Year 1Year 2Year 33-year totalPresent value at 10%
A, quick wins first1.05.08.014.011.5
B, foundation first0.07.08.015.012.3
C, foundation sliced0.56.48.014.912.3

A beats B on the year 1 scorecard by $1.0 million and loses the three-year total by $1.0 million, because the foundation's $0.5 million a month starts six months later. Discounting doesn't rescue it: the earlier benefits are too small to offset the later, larger ones.

The table hides two effects. First, if one of the four wins is a license cut on a system the foundation retires, its share of the $2.0 million is not additive once the foundation lands; every sequence overstates by that amount a year. Second, at month 12 under A, the dashboard shows $1.0 million delivered and the foundation half built. In our view, that is the point at which Kotter's error 7 becomes tempting: the program looks successful, and the hard half is still ahead.

C is the option we'd argue for. It gives up about $0.1 million against B for a real result in year 1 that is a slice of the foundation itself, so the win proves the main bet instead of competing with it.

What makes a good quick win?

We suggest five questions before a quick win gets capacity. A win that fails question 1, or any two, is, in our view, a distraction with a good name.

  1. Is it on the path? Can you trace it to the main benefit on the value driver tree or theory of change? If not, it is motion.
  2. Is it complete and in use? Weick's test: concrete, complete, implemented. A pilot launch or a signed contract is not yet a win.
  3. Is the benefit new and recurring? Would finance sign it off as additional to what the main program will deliver, and does it recur?
  4. Whose capacity does it use? If it draws on the people the foundation needs, show the foundation's new date and the value of the delay next to the win's value.
  5. What does it make possible next? Kotter's test: does the credibility it earns go into a bigger problem, such as a policy, structure or system that blocks the vision?

How should a transformation office govern quick wins?

In our view, treat them as part of the portfolio, not as a communications stream beside it:

  1. Fund wins from the same capacity plan as the foundation, so the trade-off is visible at the transformation governance forum that approves both.
  2. Report the foundation's dates next to the wins. A quick-win dashboard without the critical path invites Kotter's error 7.
  3. Record each win in the benefits register with its link to the main benefit, so double counting shows up when the foundation lands.
  4. Prefer slices of foundational work to separate projects. A first release that a business unit uses meets Weick's definition.

Quick wins are an allocation decision, and they are easier to judge when capacity, benefits and the critical path sit in one operating model rather than three separate reports.

Sources

Frequently asked questions

What step is short-term wins in Kotter's model?

Step 6. In his 1995 Harvard Business Review article, Kotter lists "Planning for and Creating Short-Term Wins" as the sixth of eight steps, and failing to do so as error 6. Kotter Inc.'s current page, based on the 2014 accelerators, also lists it sixth. He expected convincing results within 12 to 24 months, not a single quarter, and warned against declaring victory too soon.

How long should a quick win take in a transformation?

There is no standard. Kotter's window for short-term wins is 12 to 24 months, and his example product launched about 20 months into the effort. Weick sets no timescale but requires the outcome to be complete and implemented. In our view, the right length is whatever lets the win be real and in use without delaying the foundational work it depends on.

Are quick wins a bad idea?

No. Kotter, Weick, and Amabile and Kramer all give reasons why visible progress matters, from sustaining commitment to motivating people doing meaningful work. The risk lies in selection. We think wins chosen for ease, wins that borrow benefits from the main program, and wins that take the foundation's scarce people can cost more in delay than they deliver early.

How do you stop quick wins from crowding out foundational work?

Put them in the same capacity plan as the foundation and report the foundation's date next to each win. Check each win traces to the main benefit and is additional to it. In our illustrative example, doing four quick wins first won year 1 by $1.0 million but lost the three-year total by $1.0 million. Slicing the foundation into an early release recovered almost all of that gap.

Free playbook

Map how your company really operates.

Read the discovery playbook
Steve Elliott

Steve Elliott

Published November 24, 2026

More on Transformation & Value

Value levers, benefits realization.