Writing a transformation business case that survives the CFO

In brief

Use the Green Book's five case model, an optimism bias adjustment and switching values to build a transformation case a CFO can test, with a worked example.

Steve Elliott

Steve Elliott · · 6 min read


On this page
  1. What does the five case model ask a business case to show?
  2. How do you get from a long list to a preferred option?
  3. Which discount rate should a corporate case use?
  4. How should you adjust for optimism bias?
  5. Worked example: three options against business as usual
  6. What do CFOs probe in a transformation business case?
  7. What should the management case commit to after approval?
  8. Sources

A transformation business case survives the CFO when it compares real options against business as usual, adjusts for optimism before anyone sees a net present value, and names the one assumption that would flip the decision. HM Treasury's Green Book sets out a structure for all three, though its discount rate is not one a company should use.

In our view, most cases fail review not because the numbers are low but because finance cannot tell which numbers to doubt. Below, we read the current Green Book and its business case guidance, then work an illustrative case with three options, an adjusted NPV, switching values and a benefits profile.

What does the five case model ask a business case to show?

The Green Book is UK central government guidance, but in our view its structure is the most complete public method for building a business case. As of November 2026 the current edition is The Green Book (2026), revised February 5, 2026 after the Green Book Review 2025 and last updated October 28, 2026 for a change to discounting. HM Treasury's separate guidance on developing business cases, updated June 30, 2026, now combines the former project and programme guides into one document.

The guidance splits a case into five parts:

CaseWhat the guidance says it coversWhat a CFO reads it for
StrategicWhy the proposal is needed: rationale, objectives, case for changeWhether the objective is specific enough to measure
EconomicCosts, benefits and risks of different options, focused on value for moneyWhether the preferred option beats business as usual
CommercialHow the inputs will be sourced and who carries delivery riskWhich costs are fixed by contract and which are estimates
Financial"It is concerned with the affordability of the proposal."Cash timing, budget impact, accounting treatment, contingency
ManagementGovernance, delivery plan, change, benefits and risk management, monitoring and evaluationWho owns each benefit and how it will be tracked

The guidance builds the case in three stages: strategic outline, outline and full business case, moving from a preferred way forward to a preferred option to a procured deal. HM Treasury's October 28, 2026 note says the Green Book and this guidance should be "applied proportionately to the scale, cost, complexity and risk of a proposal."

How do you get from a long list to a preferred option?

The Green Book recommends, but does not mandate, an options framework filter with five categories: scope, solution, delivery, implementation and funding. The shortlist should generally hold around five options: business as usual, a do minimum, the preferred way forward, and a more and a less ambitious version of it. Business as usual must always go through to shortlist appraisal.

In our view, transformation proposals often arrive as one option and a straw man. A CFO who sees a credible do minimum can judge how much of the benefit the big program actually adds. Business as usual also needs its own cost line: if the current ERP leaves vendor support in year 3, doing nothing is not free.

Which discount rate should a corporate case use?

Not the Green Book's. The Social Time Preference Rate is a social discount rate for public spending. In its response to the Green Book Discount Rate Review 2026, HM Treasury cut it from 3.50% to 3.00% for years 1 to 30, and to 2.50% and 2.25% for later years, saying the change "will place greater value on the long-term benefits of investment". The Green Book says the rate is real and must be applied only to values in real terms.

A company discounts at a rate its finance team sets, often its cost of capital or a hurdle rate. The Green Book point that does carry over is consistency. A nominal rate goes with nominal cash flows, a real rate with real ones. This post describes methods; it is not investment advice, and the rate for your case is your finance team's call.

How should you adjust for optimism bias?

The Green Book says practitioners must adjust explicitly for optimism bias at the outset of an appraisal, by increasing estimates of costs and durations and decreasing estimates of benefits. If a public body has no evidence on its own historical optimism bias, it can use generic values in the supplementary guidance on optimism bias, first published in April 2013 and not replaced as of November 2026.

HM Treasury's June 2026 examples of appraisal calculations show how this works. For an illustrative £100 million non-standard civil engineering project, the example applies the supplementary guidance's 66% upper bound for capital expenditure, a £66 million adjustment. When a £10 million mitigation then prevents a £30 million risk, the adjustment falls to £36 million.

We think generic public works values are a poor fit for a corporate transformation. The better source is your own history: what did your last three programs cost against their approved cases, and when did their benefits arrive? If you have no record, start one, and state the uplift you used and why.

Worked example: three options against business as usual

All numbers are illustrative and come from no company. A business is considering how to transform its finance and procurement back office. Benefits are cash cost reductions against a business-as-usual baseline. Finance sets an illustrative 9% nominal discount rate and a five-year appraisal period, years 0 to 5, with no terminal value. Cash flows are nominal and fall at year end, and run costs start in year 1.

OptionOne-off costAdded run cost a yearGross benefit profile, years 1 to 5
A. Do minimum: fix and automate within the current ERP$3m, $1m (years 0, 1)$0.4m$1.5m, 3m, 3.5m, 3.5m, 3.5m
B. Preferred way forward: shared service center on an upgraded ERP$9m, $5m (years 0, 1)$1.0m$2m, 7m, 10m, 11m, 11m
C. More ambitious: new ERP and global business services$16m, $12m, $4m (years 0 to 2)$1.5m$0, 6m, 13m, 17m, 18m

Our illustrative optimism adjustments, set from an imagined internal history rather than Green Book values, raise one-off costs by 20%, 30% and 45% for A, B and C, and cut benefits by 10%, 15% and 20%. We test duration separately, as a one-year slip.

ResultABC
NPV before adjustment$5.9m$12.9m$2.6m
NPV after optimism adjustment$4.0m$4.3m−$18.8m
Switching value: further benefit shortfall39%17%Already negative
Switching value: further one-off cost overrun84%24%Already negative
NPV if all benefits slip one year (year 5 benefit lost)$1.2m−$3.4m−$30.0m
Cumulative adjusted cash turns positiveYear 3Year 4Not within 5 years
NPV over 7 years, year 5 benefits and costs held flat$7.1m$13.8m−$4.1m

The Green Book defines a switching value as "the value that a key variable would need to change to" for an option to stop being value for money, and says to calculate one at least for the preferred option. Here, B's adjusted benefits can fall only another 17% before its NPV reaches zero, and about 1% before A overtakes it. A can lose 39%.

Before adjustment, B looks twice as good as anything else; after it, B and A are nearly tied, and C fails. B is more fragile: a one-year slip in benefits turns it negative while A stays positive. And the horizon is doing real work. Over seven years B's NPV is $13.8 million, against A's $7.1 million. The Green Book's standard horizon for most proposals is 10 years. In our view, a company should set its period from the expected life of what is built, before the numbers are run.

B's adjusted benefits profile, in $m:

Year012345
Benefits01.76.08.59.49.4
Costs11.77.51.01.01.01.0
Cumulative net−11.7−17.5−12.6−5.13.311.7

Figures may not sum because of rounding. In our view, B is the better choice only if what it builds lasts well beyond five years, and then with conditions: fund it in two tranches, put each benefit line on the benefits register with a named owner, and release the year 1 tranche only when the leading measures behind year 1 benefits are on track. Our post on transformation stage gates covers that gate decision.

What do CFOs probe in a transformation business case?

In our view, a good case answers these before they are asked:

  • Is the baseline real? Benefits measured against a business as usual that already assumes cuts in the budget are counted twice.
  • Is it cash or is it capacity? Hours freed are not savings until headcount, contracts or spend actually fall. Our post on run-rate, in-year savings and cost avoidance sets out the distinctions.
  • Who owns each benefit? A benefit with no budget holder who has agreed to lower their plan is a forecast, not a commitment.
  • What drives the number? A value driver tree shows which volumes, rates and prices sit behind each benefit line.
  • Which assumption would flip the decision? Lead with the switching value, not the NPV.
  • How is it accounted for? Capitalization, restructuring charges and budget treatment belong in the financial case. They are for your controller and auditors, not the business case author, to decide.

What should the management case commit to after approval?

The business case guidance says the delivery plan, benefits register and risk register should be updated as the project is implemented. The Green Book adds that an evaluation plan should be developed as soon as a preferred option is identified, drawing on the theory of change in the strategic case.

In our view, this is where most corporate cases go quiet. The approved case should be the baseline every later forecast is compared with, so that the adjusted $4.3 million in our example is tested against what arrives, year by year. That works best when the case, its assumptions and the ledger sit in one operating model rather than in a slide deck filed after the funding meeting.

Sources

Frequently asked questions

Is the Green Book relevant to private companies?

In our view its structure is, though its rules are written for UK public spending. The five case model, the long list to short list method, optimism bias adjustment and switching values all transfer to a corporate transformation. The social discount rate and the public sector value for money tests do not. Use your own finance team's discount rate and approval rules.

What discount rate does the Green Book use as of November 2026?

The Social Time Preference Rate is 3.00% in real terms for years 1 to 30, 2.50% for years 31 to 75 and 2.25% from year 76. HM Treasury cut it from 3.50% after the Green Book Discount Rate Review 2026, and updated the Green Book on October 28, 2026. It is a social rate for public appraisal, not a corporate hurdle rate.

How much optimism bias should a transformation case assume?

There is no single right figure. The Green Book tells public bodies without their own evidence to use generic values from its 2013 supplementary guidance, which come from public projects such as civil engineering. In our view, a company should calibrate uplifts from its own past programs, comparing approved costs and benefit timing with actuals, and state the uplift openly in the case.

What is a switching value in a business case?

It is the value a key assumption would have to reach for an option to stop being value for money, for example the benefit shortfall that takes NPV to zero. The Green Book asks for switching values at least for the preferred option. In our illustrative case, a 17% further benefit shortfall wipes out the preferred option's adjusted NPV.

Free playbook

Map how your company really operates.

Read the discovery playbook
Steve Elliott

Steve Elliott

Published November 24, 2026

More on Transformation & Value

Value levers, benefits realization.