Application rationalization with the TIME model: a worked scoring of 10 applications

In brief

Score an illustrative 10-application estate on business and technical fit, place each in TIME, then price the savings and one-off costs the quadrants omit.

Steve Elliott

Steve Elliott · · 6 min read


On this page
  1. What does the TIME model actually sort?
  2. How do you score business fit and technical fit?
  3. Worked example: scoring an illustrative 10-application estate
  4. What does acting on each quadrant save, and what does it cost?
  5. Where does the TIME model mislead?
  6. How should the scoring reach a funding decision?
  7. Sources

The TIME model sorts applications into four actions, Tolerate, Invest, Migrate and Eliminate, by scoring each on business fit and technical fit. It tells you what kind of decision each application needs, but not which decisions are worth the money, so the scoring has to be followed by a costed case for every move.

In our view, that second step is where application rationalization work most often stalls. Below, we score an illustrative 10-application estate, place each application in a quadrant, then price the savings and one-off costs of acting. The quadrant chart and the costed table point to different priorities.

What does the TIME model actually sort?

TIME places each application on two axes: how well it serves the business, and how sound it is technically. The Federal CIO Council's June 2019 playbook calls it Gartner's. We could not find a public Gartner page that defines it, so we describe the quadrants as they are usually drawn:

QuadrantBusiness fitTechnical fitUsual action
InvestHighHighFund, extend, use more widely
TolerateLowHighKeep running, spend little
MigrateHighLowMove the capability to a sounder base
EliminateLowLowRetire or consolidate

US federal agencies have a public version of the same two-axis sort. The Federal CIO Council's Application Rationalization Playbook, first released in June 2019 and since revised (the current version 1.1 on cio.gov is undated), scores applications on business value and technical fit and places them in four quadrants: Reward, Review, Refresh and Remove. Reading its quadrant descriptions, Reward matches Invest, Review matches Tolerate, Refresh matches Migrate and Remove matches Eliminate. That mapping is ours. Version 1.1 does not mention TIME, but the June 2019 text listed Gartner's TIME among sample scoring methods, without endorsing it, and included an agency case study that adapted it.

In its usual two-axis form, TIME has no cost dimension; the playbook puts cost on the chart. It makes total cost of ownership a separate step, and in its placement matrix, applications with a greater TCO per user appear as larger circles.

How do you score business fit and technical fit?

Score both axes from a handful of named factors, not from a single gut rating. The playbook's factors are a reasonable start:

  • Business value: effectiveness, mission criticality, utilization, complexity and usability.
  • Technical fit: technical requirements, software and hardware version control, dependencies and interoperability, scalability and adaptability, and security standards.

We suggest a 1 to 5 scale for each factor, weights agreed before anyone scores, and 3.0 as the line, with 3.0 and above counted as high. Business owners score business value; architects score technical fit. The playbook leaves weighting to each agency and gives no formula, so the weights are a local choice and should be written down. Utilization can come from data rather than opinion, such as sign-in counts. AWS Prescriptive Guidance adds a technical signal: among its retirement use cases are zombie applications, whose average CPU and memory use is below 5 percent.

The inputs come from the application inventory: owner, cost, contract end date, integration count and end-of-support dates. Without those fields the scores rest on memory.

Worked example: scoring an illustrative 10-application estate

All numbers below are illustrative. They come from no company and are chosen to show the mechanics. Take an insurer-like business with 10 applications and $7.00 million a year in run cost (licenses, hosting, support and the people who keep each one running).

#ApplicationAnnual run costBusiness fitTechnical fitQuadrant
1Policy administration (custom, on-premises)$2.40M4.62.1Migrate
2CRM (SaaS)$0.90M4.24.0Invest
3Data warehouse (on-premises appliance)$1.10M3.82.4Migrate
4Customer portal$0.60M4.43.9Invest
5HR system A (SaaS)$0.45M3.64.2Invest
6HR system B (from an acquisition)$0.35M2.02.2Eliminate
7Legacy document management$0.30M2.41.8Eliminate
8Expense reporting (SaaS)$0.12M2.64.1Tolerate
9Departmental reporting server$0.25M2.23.6Tolerate
10Field-service scheduling (custom)$0.53M3.22.8Migrate

Now total the run cost by quadrant:

QuadrantApplicationsRun costShare of $7.00M
Invest3$1.95M28%
Tolerate2$0.37M5%
Migrate3$4.03M58%
Eliminate2$0.65M9%

The two Eliminate applications, the easy wins on the chart, hold 9% of run cost. Two Migrate applications, policy administration and the warehouse, hold $3.50 million, or 50%.

What does acting on each quadrant save, and what does it cost?

Here we price the moves, with illustrative estimates for each. Payback is one-off cost divided by steady-state annual saving.

MoveAnnual saving (steady state)One-off costPayback
Retire HR system B into HR system A$0.35M − $0.05M added SaaS fees = $0.30M$0.15M data migration0.5 years
Retire document management, archive records$0.30M − $0.04M archive = $0.26M$0.20M extraction0.8 years
Fold reporting server into the warehouse$0.25M − $0.05M added load = $0.20M$0.10M0.5 years
Move the warehouse to cloud$1.10M − $0.80M = $0.30M$1.20M4.0 years
Replace policy administration$2.40M − $1.60M = $0.80M$6.00M7.5 years

The three small moves save $0.76 million a year for $0.45 million once. The two large ones save $1.10 million a year for $7.20 million once. Notice that the third row is a Tolerate application. Its scores say leave it alone; its cost, and the fact that it duplicates the warehouse, say fold it in. The playbook's assessment step asks teams to review the inventory for duplication, which it says points to a likely business case for an enterprise solution or shared service. We treat the moves independently; folding the reporting server in first would slightly raise the warehouse's cloud run cost. Which route each Migrate move should take, rehost, replatform, refactor or repurchase, is a separate choice covered in our post on the 7 Rs of legacy modernization.

Where does the TIME model mislead?

In our view, TIME is a good conversation device and a poor decision rule. Four gaps show up in the example.

  1. Scores without cost. A quadrant has no dollar sign. The chart flags HR system B and document management as the easy wins, yet the largest saving sits in a Migrate application with a 7.5-year payback. Rank moves on saving, one-off cost and payback, not on quadrant.
  2. Dependencies. The playbook notes that applications with many dependencies are often "more challenging and costly to refactor, migrate, or decommission." Suppose policy administration has 23 interfaces. Each one adds work, and AWS lists dependencies on applications that must migrate first among the reasons to retain an application for now. Without application dependency mapping, the $6.00 million estimate is a guess.
  3. Contracts. Suppose $0.20 million of HR system B's cost is a license committed for 18 more months. The first-year saving falls from $0.30 million to $0.10 million, and payback stretches from 0.5 years to 1.5 years. A contract renewal date often decides when, not whether, an Eliminate saving arrives.
  4. Data gravity. Dave McCrory proposed the idea in 2010. He describes data as having mass; in a 2011 post quoted by InfoQ, he wrote that "Data Gravity pulls services and applications closer to the data." If the warehouse moves to cloud while policy administration, its main data source, stays on premises, every load crosses the network. Assume that adds $0.10 million a year until policy administration moves. The warehouse saving drops to $0.20 million and its payback stretches from 4.0 to 6.0 years. Sequence matters.

There is also threshold sensitivity. Field-service scheduling scores 3.2 and 2.8, close to both lines. With equal weights, raise one technical-fit factor by a point and it becomes an Invest. We think any application within 0.3 of a line should be flagged as borderline, not assigned a firm action. The 2019 playbook's TIME case study went further, splitting Tolerate into three levels and Migrate into two.

How should the scoring reach a funding decision?

We suggest four steps after the chart:

  1. Treat the quadrant as a hypothesis. It says what kind of case to write: retirement, consolidation, modernization or continued funding.
  2. Price each move. Annual saving, one-off cost, payback and the date savings can start, with the contract end and data migration costs included. The playbook warns that agencies moving on-premises applications often face what it calls a migration bubble, up-front cost before savings appear; show the bubble by year.
  3. Sequence by dependency. Retire what blocks nothing first. Move data consumers after, or with, their sources.
  4. Fund the quick paybacks and decide the big ones separately. In the example, $0.45 million once buys $0.76 million a year, a payback of about seven months before any contract delays. The $6.00 million replacement deserves its own business case, judged on risk and capability as much as run cost.

The playbook is candid that agencies often cite application total cost of ownership as the hardest part of rationalization, and its questionnaire asks respondents for cost estimates within given ranges rather than exact figures. We agree, and we think rough, labeled cost estimates beat none. In our view, rationalization holds up best when scores, costs, contracts and dependencies sit in one operating model, so next year's review starts from this year's decisions.

Sources

Frequently asked questions

What does TIME stand for in application rationalization?

Tolerate, Invest, Migrate and Eliminate. Each application is scored on business fit and technical fit, and the two scores place it in one of four quadrants: invest in strong applications, tolerate technically sound ones of low business value, migrate valuable ones on weak technology, and eliminate those weak on both. The Federal CIO Council's 2019 playbook calls it Gartner's; we found no public Gartner page defining it.

Is the TIME model enough to decide which applications to retire?

In our view, no. TIME classifies; it does not price. Before acting, each candidate needs an annual saving, a one-off cost, a payback period and a start date shaped by contract terms. In our illustrative 10-application estate, a Tolerate application paid back faster than either Migrate move once duplication and cost were counted, which the quadrants alone did not show.

How do you score business fit and technical fit consistently?

Use named factors with agreed weights. The Federal CIO Council's Application Rationalization Playbook scores business value on effectiveness, mission criticality, utilization, complexity and usability, and technical fit on factors including software and hardware version control, dependencies, scalability and security standards. We suggest a 1 to 5 scale, business owners scoring value, architects scoring fit, and a borderline flag for anything near the dividing line.

What is the difference between TIME and the 7 Rs?

TIME sorts the whole application estate into four broad actions based on business and technical fit. The 7 Rs, as AWS Prescriptive Guidance lists them, are migration strategies: retire, retain, rehost, relocate, repurchase, replatform and refactor. In practice, TIME helps decide which applications to act on, and the 7 Rs help decide how to move the ones placed in Migrate.

Free playbook

Make your organization legible to its people and its AI.

Read the playbook
Steve Elliott

Steve Elliott

Published November 23, 2026

More on Enterprise Architecture

Capability maps, TOGAF, rationalization.