02 / Fund & Optimize

What does TBM look like in practice?

One company, 3 costs, 5 decisions


The clearest way to understand TBM is to watch one company use it. This page follows Halden Freight, a fictional logistics company with $84.0 million in annual technology spend, in 2 ways. First, 3 individual costs are traced through the model from ledger to business unit. Then 5 decisions show what the model was actually used for. The company is invented. The mechanics are exactly how a real TBM model works.

Part 1: 3 costs, traced end to end

Every cost in a TBM model takes the same journey through 4 layers. Here are 3, chosen because they behave differently.

A cloud invoice line

LayerWhere it landsHow it got there
Ledger$41,200 for the month, account 6420 Public cloud, cost center 4020 InfrastructureAs booked by finance
Cost poolCloud ServicesAccount 6420 maps to this pool
TowerComputeThe cloud bill's service category is virtual machines
SolutionShipment TrackingThe resources carry the tracking application's tag
Consumer4 business units, split by tracking eventsEnterprise Accounts takes 13.8%, or $5,686

This is the easy case. Cloud data is detailed and tagged, so the path is direct at every step.

A salary

LayerWhere it landsHow it got there
Ledger$11,500 for the month, account 6100 Salaries, cost center 4020 InfrastructureA database engineer's loaded monthly cost
Cost poolStaffingAccount 6100 maps to this pool
TowerDataThe infrastructure team is split by headcount. This engineer is on the database group
Solution6 solutionsSplit by database storage each solution uses. Shipment Tracking takes 23%
ConsumerFollows each solution's own driverFor the Shipment Tracking share, by tracking events

This is the hard case. A person supports many things, and each step needs a rule. It is why labor is the pool that most rewards good data.

A software subscription

LayerWhere it landsHow it got there
Ledger$54,000 for the month, account 6510 Software subscriptions, cost center 4030 WorkplaceThe office productivity suite
Cost poolSoftware & SaaSAccount 6510 maps to this pool
TowerEnd UserThe product is workspace software
SolutionWorkplaceDirect. It is part of the standard workplace bundle
ConsumerEvery business unit, by active usersEnterprise Accounts has 420 of 6,400 users, or 6.6%

This one is direct at the tower and solution steps and proportional at the last. Per-person costs split by people is one of the few cases where a headcount driver is the right one.

In all 3, the amount never changes. It is the same money described 4 ways.

Part 2: 5 decisions the model informed

A model earns its cost when it changes a decision. These are 5 that Halden made differently because of it.

1. Finding the source of a cloud overrun

The question. Infrastructure finished the year $830,000 over budget. Why?

What the department report said. Infrastructure is 4% over.

What the model said.

CauseAmount
Tracking and portal usage ran ahead of plan+$620,000
Commitment discounts lowered the cloud rate−$110,000
An unbudgeted data migration+$320,000
Total+$830,000

The decision. The usage growth was funded, because it came from customers. The unbudgeted migration led to a new rule that project infrastructure must be approved with the project. Nobody was blamed for an overrun that was mostly good news.

2. Choosing which applications to retire

The question. Halden runs 212 applications. Which ones are not worth their cost?

What the model added. The full cost of each application, including the people, infrastructure, licenses, and support that sit in different departments, set against how many people use it.

ApplicationAnnual costActive usersCost per user
Fleet Docs Archive$260,0009$28,889
Legacy Dispatch Console$410,00022$18,636
Yard Scheduler$340,000610$557
RateCalc v1$180,0000Not in use. Replaced last year

The decision. 14 applications were retired, saving $1.3 million a year. Before the model, nobody could see the full cost of the first 2, because no single budget held it. The fourth was still being paid for a year after its replacement went live.

3. Changing behavior with showback

The question. Why is tracking more than half of Enterprise Accounts' technology cost?

What the model showed. 2 customers' systems were checking shipment status every few seconds, generating a large share of 18.4 million tracking events a quarter.

The decision. Those integrations were changed to send updates only when status changes. Events fell to 14.9 million. Enterprise Accounts' charge fell by $73,500 a quarter, and Halden's real cost fell by about $22,000, because most of the platform's cost is fixed. Both numbers were reported.

4. Pricing a premium service

The question. Should Halden charge enterprise customers more for real-time tracking?

What the model showed. The technology cost of tracking one shipment, by type of customer.

Tracking events per shipmentTracking cost per shipment
Regional customersAbout 10$0.21
Enterprise customersAbout 31$0.64

The decision. Enterprise shipments cost 3 times as much to track. Sales had been including real-time tracking in enterprise contracts at no charge. It became a priced feature, with the cost per shipment as the floor.

5. Defending next year's budget

The question. The business plans to ship 12% more next year. What does that do to technology cost?

What the model showed. For Shipment Tracking, a 12% rise in volume means a 3.6% rise in cost, from $11.2 million to $11.6 million, because only about 30% of the service's cost varies with volume.

The decision. The budget was approved without the usual argument. Finance could see that the increase followed the business plan, and that unit cost was falling.

What the 5 have in common

None of these decisions needed a complete model. Each used one slice of it:

DecisionLayers needed
Cloud overrunCost pools, towers, solutions for cloud spend only
Application retirementTowers and the Application tower in detail
ShowbackAll 4 layers, for one business unit
Premium pricingOne solution and its driver
Budget defenseOne solution, with fixed and variable split

That is the argument for building a model one decision at a time. See how to implement TBM.

Where TBM is used in the real world

TBM is used across large enterprises and the public sector. Government adoption is the easiest to verify, because the documents are public. The United States federal government has required agencies to report information technology spending using TBM cost categories, and several state governments have built TBM programs. Public sector IT budget documents organized by cost pool and tower are a good place to see the taxonomy applied at scale.

Get the full model

The complete Halden Freight workbook, with every mapping and allocation rule, is in the TBM template pack.

Questions leaders ask

What is an example of TBM?

A company traces its cloud bill from the general ledger to the Cloud Services cost pool, to the Compute tower, to the service that uses it, and then to the business units that consume that service, so each unit sees what it costs.

What decisions does TBM support?

Common ones are retiring applications, explaining budget variances, setting showback or chargeback, pricing services, and building next year's budget from business demand.

What is a TBM use case?

A TBM use case is a specific decision or question the cost model is built to answer, such as which applications to retire or where a cloud overrun came from.

Who uses TBM?

Large enterprises and public sector organizations with significant technology budgets. It is used by CIOs, CFOs, IT finance teams, and business unit leaders.

Last reviewed 2026-11-26